Texas Pauses Data Centers Until It Learns How Much Texas They Need
Abbott’s September directive extended the pause to environmental permits while agencies sought water, power and ownership information.
AUSTIN—Governor Greg Abbott ordered Texas environmental regulators on September 21 to stop issuing permits for data centers until other state bodies completed their audits. The state’s ambitions for artificial intelligence had reached the portion requiring an inventory of water and electricity.
The directive covered permits handled by the Texas Commission on Environmental Quality. Abbott wanted information about power demand, water use, ownership, local impacts and tax breaks before approvals continued. The paperwork concerned resources that the proposed buildings would consume whether or not the paperwork was complete.
An earlier pause focused on new connections to the electric grid. That left an obvious complication: some projects planned to generate their own power. An environmental-permit pause could reach developments that did not need the same grid-connection permission.
The Tribune reported that as few as 28 percent of data centers had responded to a separate mandatory water-use survey. Statewide planning was therefore being asked to account for an industry that had not fully accounted for itself.
Abbott had previously promoted Texas as an AI development hub. The September directive added a preliminary question to that ambition: what, precisely, would the hub be drawing from the places around it? October’s enforcement dispute would test what the pause actually stopped.
Sources: The Texas Tribune: Abbott extends data-center pause to environmental permitsGovernor Abbott: September 21 directive to TCEQ