Texas Resumes Data Center Permits Before Sharing The Completed Picture

Environmental reviews have restarted. ERCOT's full findings are scheduled for December, leaving the public to wait while the paperwork moves.

Blank plans and a clipboard sit on a utility cabinet outside an anonymous data center and electrical substation.
The permit desk has reopened. The public report has a later appointment. (Whisker-Leaks editorial illustration)

AUSTIN—Texas environmental officials have resumed reviewing data center permits, moving the process forward ahead of the scheduled release of the grid operator’s full findings. The Texas Tribune reported the change on November 17.

TCEQ said Gov. Greg Abbott’s office had notified it that grid officials finished collecting community-impact information. The agency said it would return to its normal permit process under applicable law.

ERCOT reported responses from 93% of 465 projects in its November 5 update. Its full findings are scheduled for December 10, with discussion at the Public Utility Commission on December 17.

That sequence differs from the longer pause Gov.-elect Gina Hinojosa advocated while lawmakers prepare new protections. Restarting environmental review also does not establish that every separate grid or water issue has been resolved.

The agencies have enough information to announce that collection has ended. Communities will receive the fuller explanation on the later dates, while the permit applications resume their earlier movement.

Sources: The Texas Tribune: TCEQ resumes reviews and ERCOT sets December reporting datesThe Texas Tribune: the incoming governor's proposed longer pauseERCOT: November 5 community-impact information request update to the PUC